December 2024

The barrel shed has undergone a complete transformation and is now beautifully organized, featuring all of our barrels stored neatly and efficiently. Each barrel has its designated spot, ensuring that everything is easily accessible and arranged in an orderly fashion. This meticulous organization not only enhances the overall aesthetic of the shed but also improves functionality, making it easier for us to manage our inventory.

May 2024

The cool room wall was finally completed after several days of Richard and Jason erecting panels, drilling, and pop riveting.

September 2024

Construction began with the boring of the post holes, which reached approximately 6 meters deep into the natural earth on the west side. Subsequently, the shed was erected. After some delays, the roof was eventually completed.

May 2024

Demolition of the old pig shed was the starting point to prepare the pad for the new barrel shed. Shifting dirt & rocks, lots of hard sold rocks from the high side to the low side. Then Clare Quarry delivered 1500tonnes yes that's right a s*&%t load of fill that was watered & compacted over the span of 6 weeks.